a contractor estimates that he can paint a house in 5 days using 6 men. if he actually uses 5 men for the job, how many days will they take to paint the house?

Respuesta :

Einstein08 Einstein08
  • 01-09-2018
it will take 4 days to paint the house with 5 men
Answer Link
tramserran
tramserran tramserran
  • 01-09-2018

1 house = 6 men x 5 days  = 30 man days

Need 30 man days with only 5 men: 30x = 5 men   →  x = 6

It will take 6 days for 5 men to complete the job.

Answer: 6 days


Answer Link

Otras preguntas

what are the importance of gross margin pricing?
I need help! question is in the image (15 points)
0.3 is 10 times as great as what decimal? 0.003 is 1 half of what decimal?​
Tìm giá trị lớn nhất,nhỏ nhất của A = sqrt(x - 4) + sqrt(10 - x)
evaluate -6_____-2 =
one thing at world that all want and don't want to lose what is that​
· Alicia makes $11.00 an hour for her normal 8-hour shift. She worked 5 hours overtime at double. How much did she make for the ot hours?
Other than the first shell, which can hold up to 2 electrons, how many electrons will make a "full" valence shell? 6 1 8 4
Girls and boys are different and growth rates and patterns true or false
Read this story and then answer the question that follows: Sarah saw them, again. Out of the corner of her eye she could see the kids ganging up on the new girl