If your procurement budget request did not provide for buying a whole number of useable end items, this would be a violation of which funding policy?

Respuesta :

Manetho
Manetho Manetho
  • 06-01-2020

Answer:

Full funding policy.

Explanation:

This would be a violation of Full funding policy.

Full funding strategy is a federal budgeting requirement implemented by Congress in the 1950s on the Department of Defense (DOD) that mandates all acquisition expenses of a weapons or piece of military equipment to be financed in the year the object is procured. Hence in the above example there is violation of Full funding strategy.

Answer Link

Otras preguntas

Can I get step by step explanation for how to get the equation 5x+15+5y=10x into function form for graphing
does hamilton believe the government's power should be strong or weak?
what caused the quiet depression during the 1920s
What did many people in the North believe after the Supreme Court’s ruling in the Scott v. Sandford case?
Which leader do you think most helped the patriot cause?
what does common and proper noun mean
Why did some leaders believe that unicameral legislatures created more democratic governments?
napisz sprawozdanie z wycieczki
The relationship between newspaper readers and newspapers is most like that of _____.
Which statement best describes why many Southerners supported the Kansas-Nebraska Act? A.It extended the Missouri Compromise to those areas. B.It allowed ensl