When looking at a program board at the end of program increment (PI) planning, what does it mean when a feature is placed in a team's swim lane with no strings

Respuesta :

IfeanyiEze8899 IfeanyiEze8899
  • 04-01-2021

Answer:

It simply means that other teams can independently complete the feature.

Explanation:

PI or program increment is a planning interval during which an agile release train (ART) plans and produces working and tested software and systems. It takes a duration of 8 to 12 weeks

Agile teams can access and independently complete various ARTs found in their swim lanes with no strings.

Answer Link

Otras preguntas

the graph below shows the distribution of students grades on their last math test. Based on the Empirical rule, what percent of students made.. *btwn 80 n 85 o
What is a synonym for sensory language?A.simileB.fluencyC.metaphorD.imagery im thinkin D?
how can bureaucratic personality be dangerous
David helped his father stock the pond with baby catfish and blue gill. They put in a total of 75 fish. If the number of blue gill was doubled and the number of
find a common solution for each system of equations: y=3x+5 y=-5x-3
Please answer:If a stadium holds 60000 people.1. If the stadium is 2/3 full, how many people are there?2. If the stadium is 3/4 full, how many people are there?
Find 4 consecutive even integers where the product of the two smaller numbers is 72 less than the product of the two larger numbers?
What is the solution: (9x+2)(4x^2+35x-9)=0
how can bureaucratic personality be dangerous
where did japan first expand its empire after 1930