Mr. Kumar is getting his house renovated. 1/5 th of the work has been completed in 2 months. How much time will it take for the entire work to be completed?

Respuesta :

liam2747
liam2747 liam2747
  • 02-05-2021

Answer:

10 months

Step-by-step explanation:

If it takes 2 months to do 1/5th, it will take 4 months to do 2/5, 6 months to do 3/5, 8 months to do 4/5, and 10 months to do 5/5 or in other words the whole thing.

Answer Link

Otras preguntas

at what point do scientists classify an area's weather as its climate? 1 year ,5 years ,15 years or 30 years
If 2x+z=2y and 2x+2y+z=20 what is the value of y?
translate into an equation. Five times the sum of twice a number, x, and six is thirty. Find the number.x = Translate into an equation. The difference b
How far does Franklin Roosevelt deserve his reputation as one of the greatest US presidents?
Adam tried to compute the average of his 7 test scores. He mistakenly divided the correct sum of all of his test scores by 6, which yielded 84. What is Adam’s c
Simple Machine Lever: A ________ that pivots on top of a fixed point called a _______.
which organism would more closely resemble it's parent,one produced by asexual reproduction,or one produced by sexual reproduction? why?
Can you give me the order of Biomes from coldest to hottest please?-tundra-taiga-temperate deciduous forest-temperate grassland-temperate woodland (chaparral)-d
What is the value of the 8 and 48?
Three individuals form a partnership and agree too divide the profits equally. X invest -9,000 , Y invest 7,000, Z invest 4,000. How much less does X receive if