8 students take 18 hours to construct a raft.
If the raft needs to be completed 12 hours earlier, calculate how many more students are needed.

Respuesta :

devishri1977
devishri1977 devishri1977
  • 04-08-2021

Answer:

16

Step-by-step explanation:

Students                      8       x

Time taken (hours)     18     18 - 12 = 6

If number of students increases, the work will completed in less hours.

So inverse proportion

[tex]x =\frac{18*8}{6}=3*8 = 24[/tex]

Additional students required = 24 - 8 = 16

Answer Link

Otras preguntas

CAN SOMEONE HELP WITH THIS WILL GIVE 5 STARS
A small diameter, 11 cm long solenoid has 258 turns and is connected in series with a resistor and battery. The size of the magnetic field inside the solenoid i
How are the points of view in Passage 1 and Passage 2 different? The author of Passage 1 is excited about gardens, but the author of Passage 2 is unhappy about
Given q(x)=3x and r(x)=x2. What is (r∘q)(2)? 36 10 12 24
When writing about a work of art, which question would contribute most to your evaluation? o Where is it today? O Why is it important? O Who is the artist? O Wh
Write all the words in alphabetical order
what can the nitrogen cycle not live without
Please select the word from the list that best fits the definition Occurs when chlorophyll in a plant traps light energy and produces sugar A) Respiration B) Ph
An object on a planet has a mass of 243 kg. What is the acceleration of the object, if the radius of the planet is 2.32 x 10^7 m , and the mass of planet is 603
Divide 5 1/7 ÷ 2 2/5 answer in simplest form​